Work in strategic Zojila tunnel halted after recent avalanches

Date:

Share post:

Donate-GC-Razorpay

Srinagar: The work in strategic Zojila tunnel along the Srinagar Leh highway has been halted after a recent series of snow avalanches in Ganderbal district of Jammu and Kashmir left two workers dead.

Officials said this is for the first time after the construction of the 13-km long Zojila Tunnel commenced in April 2021, the work has been stopped from Kashmir side.

The work on the tunnel- which will connect Sonamarg in Kashmir with Minamarg in cold desert Ladakh- is being executed by Megha Engineering and Infrastructure Ltd. (MEIL).

Project head of the MEIL, Harpal Singh said the works on the tunnel were in full swing till January 10.

“But series of avalanches and keeping in safety of our workers, the work on the tunnel has been stopped from the Kashmir side,” Singh told UNI. “ After we were awarded the tunnel construction work, we never stopped work. This is the first time that work has been halted and may remain suspended for a month.”

Singh, however, said the work on the Minamarg Ladakh side of the tunnel is still underway.

“Minamarg is not an avalanche prone area and the previous night the temperature there was minus 30 degrees and even the day temperature is around minus 10. But work is underway on that side,” Singh said.

After the recent snow, a massive snow avalanche hit Serbal village close to the under construction tunnel on January 12 killing two labourers from Kishtwar district of Jammu and Kashmir. Two days later another snow avalanche hit the area and according to officials the avalanches transported about 50,000 metric cubes of snow.

Zojila tunnel and 6.5-km Z-Morh tunnels are part of a strategic project for ensuring round-the-year connectivity between Kashmir and Ladakh region which remains closed during the winters due to heavy snowfall.

The deadline to complete the Zojila project is November 2026 but there is likelihood that it may be completed ahead of its deadline.

The all-weather connectivity will provide a lot of relief to the Army and the local people. The Indian Army has been facing a hostile China along the Line of Actual Control in Ladakh since May 2020.

Related articles

Bharat’s Trailblazing Renaissance in Energy Transition

“The world is looking up to India. Those who saw India as slow and steady, can now see...

When Rivers Remember: India’s Ganga Gambit in the Shadow of the Indus Waters Treaty

In the small riverside town of Rajshahi in Bangladesh, 58-year-old farmer Abdul Momen wakes at dawn, not to...

Ditch the Spoon and Fork: Embrace the Indian Way of Eating with Your Fingers

 In an age where we’ve outsourced even our chewing to convenience, where children eat pizza with a fork...

After Delhi’s Yash Kumar Murder, Victim’s Family Receive Death Threats

In yet another tragic incident that sent shockwaves around the national capital and beyond, 20-year-old Yash Kumar was...